SHELL Moves Toward A Beaver County Cracker Decision

Shell CrackerRobert Johnson
President, ADKL

 

…..
….

Royal Dutch Shell (“SHELL”) is moving carefully and methodically toward a final decision on their much awaited Beaver County natural gas cracker facility.

SHELL conducted a community forum at the Beaver County Community College Golden Dome on May 28, 2015.  This has been one of a series of forums sponsored by SHELL to provide updated information   regarding the proposed cracker facility as well as address questions from the public. It was an example of how carefully and methodically going about making its final decision on its proposed cracker facility, working with the community.

beaver county

Community College of Beaver County

There were a number of speakers at the fourm making brief presentations highlighted by Jeff Krafve, SHELL Project Manager.   Some of the topics covered were public safety, economic impact, transportation, parking, noise, water, and air quality, potential environmental waste from the facility, and support of community/non-profits.

SHELL staff highlighted their support of the Beaver County Conservancy, United Way, and other nonprofit activities.  Upon final approval of the project, Route 18 will be moved along with the current I-376 interchange location.

Regarding possible plant environmental waste issues, SHELL plans to reuse all by- products and emphasized that little to no waste remains as a result of their manufacturing process.   SHELL proudly emphasizes being a good “environmental steward” and they will prioritize public safety.  They promise to do their best to operate the plant around existing work and school activities in Beaver County.

Finally, SHELL is also reviewing noise suppression technology to keep plant noise to a minimum.  They are also planning to treat water on site.

beaver county - another Cracker elsewhere

Cracker Facility

As far as making the final decision to build the cracker plant, SHELL is considering three factors:

  1. Obtaining all of the necessary public permits (air quality permit is pending).
  2. There must be enough feedstock (wet gas supply) to keep the plant operating long-term into the future.
  3. The cracker plant must make economic sense for the Shell portfolio.

There was no discussion about a decision date so stay tuned.  SHELL plans to have another community forum within a few months where the main topics will be jobs and opportunities.  For more information about the SHELL cracker facility please go to:   www.shell.us/poly-e or email to shellchemicalsproject@shell.com

SHELL officials are to be commended for planning this forum.  It was very informative and well done.

beaver county

Robert Johnson is President of ADKL and may be reached at rjohnson@adkl.org.

Please share this post and get the word out everywhere!

2 thoughts on “SHELL Moves Toward A Beaver County Cracker Decision”

  1. Too bad it could not have come to New York? We are stuck with Wall street ,pv and wind pretend energy? I hope you can get it up and running fast! It will sure help build a stronger manufacturing base for all Pa.

  2. Pingback: Shell community forum on Cracker Facility - A Different Kind of Lobbyist

Leave a Reply

Your email address will not be published. Required fields are marked *