Powered by Max Banner Ads 

Delaware Riverkeeper Earning Title As the Biggest Loser

delaware riverkeeper - Jim Willis reports

Jim Willis
Editor & Publisher, Marcellus Drilling News (MDN)

… 

There are few organizations more litigious or nasty than the Delaware Riverkeeper. It’s earning a reputation as the “biggest loser” with the Federal Courts.

The U.S. Court of Appeals for the District of Columbia Circuit slapped down THE Delaware Riverkeeper in yet another crushing defeat for the virulent anti-fossil fuel organization (and mouthpiece for the William Penn Foundation, its main funder). Even though Williams’ Transco Leidy Southeast expansion project went online some 18 months ago, Riverkeeper sued the Federal Energy Regulatory Commission (FERC) some 14 months ago over its approval of the project.

delaware riverkeeper

Leidy Southeast was/is 30 miles of additional pipeline segments laid next to existing pipe, called loops, in Pennsylvania and New Jersey, along with upgrades at several compressor stations. The project bumped up the capacity of the mighty Transco pipeline by an extra 525,000 dekatherms of natural gas per day–enough natural gas to serve 2 million homes. The project means more Marcellus gas now flows south to new markets.

Riverkeeper claimed FERC should not have approved the project until PA had issued federal 401 stream crossing permits under the Clean Water Act. It was a “procedural” objection. That is, Riverkeeper claimed FERC did things out of order and should be, we don’t know, shut down? Punished? Flogged? Prevented from doing it ever again?

Riverkeeper also went after PA and NJ after they issued the 401 certificates, saying they shouldn’t have. The Third Circuit Court of Appeals (in Philadelphia) rejected that argument last August. The new news is that the U.S. Court of Appeals for the District of Columbia Circuit has now rejected Riverkeeper’s case against FERC.

delaware riverkeeper

The justices said FERC is free to approve projects prior to states issuing 401 certificates because a project approval still doesn’t mean the project will get built–unless the states DO issue those 401 certificates. It all sounds rather complicated to follow. The short version is this: Delaware Riverkeeper lost yet another court case against a pipeline project.

We have a full copy of the court’s ruling below. Here’s a summary/explanation of the case, from a lawyer with Van Ness Feldman (emphasis added):

On May 23, 2017, the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) issued Delaware Riverkeeper Network v. FERC (Riverkeeper). The decision upholds the Federal Energy Regulatory Commission’s (FERC) practice of issuing conditional certificates to natural gas pipelines under section 7 of the Natural Gas Act (NGA), prior to a pipeline applicant’s receipt of a Clean Water Act (CWA) 401 certification.

Riverkeeper rejected the Delaware Riverkeeper Network’s (DRN) argument that FERC’s conditional approval of the Transcontinental Gas Pipe Line Company, LLC (Transco) Leidy Southeast Project (Leidy Project) violated the CWA’s sequencing requirement. The CWA prohibits federal agencies from authorizing any activity that “may result in any discharge into the navigable waters,” before a CWA section 401 certification has been issued by the state in which the discharge may occur. The court considered whether FERC acted unlawfully when it issued the certificate before Transco obtained a CWA section 401 certification from Pennsylvania. It ultimately held that FERC did not violate any sequencing requirements because the conditional approval was merely the pipeline’s “first step” towards obtaining construction approval. In fact, the certificate explicitly conditioned Transco’s construction approval on the pipeline obtaining a CWA section 401 approval from Pennsylvania. Therefore, absent a Notice to Proceed with construction activity, FERC’s conditional certificate provided Transco with no authority to proceed with activity that could result in a discharge or violate the CWA.

Riverkeeper also upheld FERC’s environmental analysis of the Leidy Project under the National Environmental Policy Act (NEPA), which the court explained is a procedural statute that serves an informational function but does not mandate particular results. DRN had argued that FERC’s wetlands analysis violated NEPA by failing to follow the Pennsylvania or “Cowardin” wetlands classification systems. The court held that FERC took the requisite “hard look” at the impact of the Leidy Project on the environment, evidenced by the fact that it disclosed and applied its methodology for evaluating and classifying wetlands, and met NEPA’s informational requirements. The court also found that DRN failed to substantiate additional arguments that FERC’s gas flow analysis of the Leidy Project was technically deficient or violated NEPA.

Riverkeeper notes that FERC’s interpretation of the CWA, with respect to issuing a certificate prior to Pennsylvania issuing the 401 certification, deserves no agency deference because the U.S. Environmental Protection Agency, as opposed to FERC, is the agency charged with administering that statute. Therefore, it reviewed FERC’s compliance with the CWA de novo. However, the case could be read as acknowledging the broad authority FERC has to administer the NGA. Riverkeeper’s holding clarifies that FERC has sufficient flexibility to consider and certificate a project in several stages, including the issuance of a conditional certificate prior to a Notice to Proceed with tree felling or construction. The court also paid FERC’s NEPA review considerable deference by reiterating its prior refusals to “flyspeck” FERC’s NEPA findings in search of minor procedural deficiencies. Without suggesting that FERC engaged in this type of behavior, the court explained it would not require precise compliance with NEPA procedures when evaluating allegations of agency error.

Riverkeeper now joins a series of recent D.C. Circuit decisions that rejected environmental groups’ attempts to quash energy infrastructure projects using allegations of procedural deficiencies. To make its point, the court cites to several of its recent precedents, including Sierra Club v. FERC (2016) (holding that FERC’s decisions were not deficient under NEPA because the challenged activity, increased commodity exports of liquefied natural gas, was regulated by the U.S. Department of Energy and not FERC); Myersville Citizens for a Rural Community, Inc. v. FERC (2015) (holding that FERC’s alternatives analysis was sufficient to satisfy NEPA and that FERC’s consideration of the project’s negative impacts was adequate under NEPA); and Gunpowder Riverkeeper v. FERC (2015) (limiting relief under NEPA to environmental, as opposed to economic, harm). The court also distinguished Riverkeeper from a 2014 proceeding of the same name (2014 Riverkeeper) in which the court reversed and remanded a FERC order that granted a different pipeline a NGA section 7 certificate. 2014 Riverkeeper found that FERC violated NEPA and its regulations by failing to review connected, cumulative, or similar actions when its environmental review neglected other pipeline projects in the same general vicinity and sponsored by the same pipeline operator. The 2014 Riverkeeper decision marks the only successful appellate challenge by an environmental group of a FERC certificate order on NEPA grounds. The case has already been distinguished repeatedly in later D.C. Circuit decisions, including the three described above. By distinguishing it again, Riverkeeper suggests either that the holding in the 2014 Riverkeeper case is the exception and not the rule, or that FERC is doing a better job at NEPA compliance.

Equally important to the questions the Riverkeeper case did answer, are the questions it did not answer. For example, the court refused to consider whether letter orders authorizing pre-construction tree-felling prior to the CWA section 401 certification impermissibly approved activity that could result in a discharge into navigable waters. The court determined that Transco’s letter orders for the Leidy Project were not appropriately before it on review because they had not been independently challenged by DRN. However, pipeline applicants and regulators should be aware that future legal challenges to notices to proceed are possible if the challenger follows proper appellate procedures.

Delaware Riverkeeper Network v. FERC Ruling

delaware riverkeeper

An MDN aside: For years, after reading a suck-up profile of Maya van Rossum referring to her as The Delaware Riverkeeper, we’ve referred to the organization as THE Delaware Riverkeeper here on MDN. Because Riverkeeper is essentially van Rossum, an assistant and a lawyer. But mainly just van Rossum. Look at the case title below. It lists Maya van Rossum by name, followed by her title–“The Delaware Riverkeeper.” And you thought we were just being funny and sarcastic all this time. Nobody would deign to call themselves THE Delaware Riverkeeper, right? Well, here’s proof positive that we’ve been accurate all along! 

For more great articles on natural gas development every single business day, subscribe to Marcellus Drilling News using this convenient link.

Print Friendly, PDF & Email
Email this to someoneShare on FacebookShare on LinkedInShare on Google+Digg thisFlattr the authorShare on RedditShare on YummlyShare on StumbleUponTweet about this on TwitterShare on TumblrBuffer this pagePin on Pinterest

5 thoughts on “Delaware Riverkeeper Earning Title As the Biggest Loser

  1. https://thinkprogress.org/senate-committee-holds-ferc-confirmation-hearing-81932d3b5506

    Speaking of Maya and “the” riverkeeper and this insane movement, looks like think progress has covered beyond extreme energy’s most recent tantrum. Oddly or perhaps not so oddly think progress failed to mention the word fracking in the headline. Is it in the story even?

    What is the deal with ferc again according to this movement? It’s a rogue agency (didn’t Robert kennedy jr associated with a different riverkeeper say that on television years ago?)! It’s an enemy of the people too I hear. Fascinating stuff always!

  2. gas and pipeline corporations, and their rubber stamping FERC and editorialists are the biggest losers in the court of public opinion

  3. Their funders aren’t getting their money’s worth from these losers. Maybe time to shut them off.

Leave a Reply

Your email address will not be published. Required fields are marked *


 Powered by Max Banner Ads